The Waubee Lake Trail cleared its last local hurdle this month. The Times-Union reported on Oct. 14 that town attorney Jay Rigdon told Milford Town Council the right-of-way purchases are complete. The town now owns the final two parcels, holds the titles, and has state certification of ownership. That was the last part of the project Milford could finish by itself. The next dates, including when bids open, what the trail costs and when crews arrive, now follow the Indiana Department of Transportation's calendar.
The last piece Milford controlled
For most of this year, the land held everything else up. In February, InkFreeNews reported that the bid date had slipped from September 2026 to Jan. 13, 2027 because right-of-way acquisition was running behind. Bids could not go out until the town owned every parcel along the route.
That condition has now been met. INDOT's 18-month construction letting list, dated Oct. 15, 2026, carries the project as contract R-44340, "Milford Trail: 1st St to Waubee Lake Park." The list shows right-of-way status as clear, sets the letting date at Jan. 13, 2027, and gives Oct. 21, 2026 as the ready-for-contract date. INDOT runs the bidding even though the town manages the project locally, so the schedule is now set inside INDOT's bidding system.
Where the trail will actually run
The route has been in the planning documents for years, but many people know it only as "town to Waubee." The most detailed description is in a December 2024 public notice in The Mail-Journal. It traces the path in five segments:
- Start on the south side of East First Street near downtown Milford.
- Run along the east side of the Norfolk Southern tracks.
- Cross Turkey Creek on a prefabricated pedestrian bridge, then follow a tributary to County Road 1150 North.
- Head east along the south side of 1150 North.
- Turn south along the west side of Camp Mack Road into Waubee Lake Park.
The trail is designed as a 10-foot-wide, ADA-compliant asphalt multi-use path. Plans include a trailhead with sidewalk, parking and a resting area. When USI Consultants presented its feasibility work in 2021, InkFreeNews reported the total length as 1.12 miles, a short link between the middle of town and the lake.
Six years of price tags, and what each one measured
The cost figures reported since 2020 are hard to compare because each measures something different. Some are early estimates, some are all-in project values, and one covers construction only. Here they are in order:
| When | Figure | What it measured |
|---|---|---|
| 2020 | $6,000 | Feasibility study with USI Consultants |
| February 2021 | $1,095,200 | Federal 80/20 matching grant the town had applied for |
| November 2021 | About $1.7 million | Project estimate at the time of reapplying for federal funds |
| March 2022 | $978,400 | Federal transportation funding awarded through INDOT |
| October 2023 | $1.77 million | Estimated total, with Phase 1 plans 30% complete |
| December 2024 | About $1.763 million | Engineering, right-of-way and construction combined |
| February 2026 | $2.5 million | Reported overall project value |
| June 2026 | $1.6 million | INDOT's estimated construction amount |
The 2022 award is the main source of money. InkFreeNews reported in March 2022 that INDOT awarded Milford $978,400 in federal transportation funds for the trail. The program requires a local match of at least 20%, and INDOT would also take part in design, engineering and right-of-way costs. At the time, the town said it had asked for $1.4 million against a $1.7 million estimate and would have to find the difference.
That difference has grown. In February 2026, Clerk-Treasurer Tricia Gall estimated the town's share at about $750,000, up from roughly $342,000 before the pandemic, according to InkFreeNews. In April, the Times-Union reported that the local portion was expected to come from $500,000 in local income tax plus $250,000 from K21 Health Foundation, and that less tax money would be needed if another grant came through. The council also approved $105,000 in extra charges that month for redesign, bridge design, railroad coordination, engineering and archaeological work. The K21 amount is reported two ways. Gall reported a secured $200,000 grant in February, and the April report lists $250,000.
Why the route stayed where it is
The 1150 North segment is the one stretch residents have publicly debated. At the March 9 council meeting, two residents brought a safety concern about the roughly 1,200 feet of trail planned along the south side of the road, which crosses several driveways and entrances. They suggested moving that piece to the north side, behind the homes there, InkFreeNews reported.
Council President Doug Ruch said the trail's technical committee had already looked at the north side. He said the soils behind those houses "were questionable, they would require more expense," and that keeping the trail in existing right-of-way meant "nothing's really going to change in the right of way." The deadline settled it. Councilman Jim Smiley said the town "wouldn't make our timelines" if it changed the route. Beth Johnson of USI Consultants explained that missing those deadlines would forfeit matching dollars for the rest of the project, and that construction is the largest part of it.
Gall told the council that soil testing, trail design, right-of-way acquisition and appraisals had already cost about $350,000, and that the town would not get that money back if the project stopped. Vice President Ken Long summed up the council's position: "The die is cast, essentially. It's going to go forward like it is." The route stays as designed because the federal money depends on keeping to schedule.
What Jan. 13 decides
Contractors' bids, due at the Jan. 13 letting, will produce the first real construction price. In February, Gall said the construction cost would not be known until bids came in. INDOT's June 2026 request for construction-inspection services put the estimated construction amount at $1.6 million, funded 80/20.
If bids come in close to that estimate, the local-match plan from April should hold. If they come in higher, the town's share rises with them, since the federal award is a fixed amount. Either way, the January bid opening will show whether local income tax money is still needed or another grant can cover part of it.
For timing, the best available guide is the 2024 public notice. It forecast construction starting in January 2027 and lasting about 12 months. The letting has since landed on Jan. 13. A contract award and contractor mobilization come after that, so actual digging would start later in 2027. If the 12-month estimate holds, the trail would open sometime in 2028. Treat that as a projection from a 2024 forecast. No contractor has signed a schedule yet.
Main Street is waiting on a federal timeline too
The trail is not the only Milford project waiting on a federal agency. A few blocks away, temporary fencing went up on July 29 at the former PNC Bank building, 127 S. Main St. The Milford Post Office is set to move there from 126 S. Main St., directly across the street, InkFreeNews reported in August.
That move has its own long history. USPS first told the town council in 2020 that it planned to relocate, and it named the PNC building in 2021. The move was supposed to be finished in June 2025 but went on indefinite hold when construction costs rose. As of August, a USPS spokesperson expected the remodel by DLZ Corp. of Columbus, Ohio, to be done in spring 2027. No opening date has been announced, and the current post office stays open until further notice.
The trail and the post office both took about six years, lost time to rising costs, and now have firm dates set by agencies outside town hall. Neither one depends on another council vote to move forward.
A few nearer dates for this fall:
- Oct. 24, 4 to 8 p.m. The council approved LITE Recovery's request to close Catherine Street from the alley to Henry Street for a Halloween trunk-or-treat with hayrides.
- Leaf pickup is underway. The town asks residents to place leaves at the curb in narrow strips with no rocks, sticks or trash, keep piles away from vehicles and poles, and not put them in alleys, where they won't be picked up.
- Milford Public Library, 101 N. Main St. Curbside pickup continues while elevator repairs take longer than planned. Fall Family Story Time runs Wednesdays through Nov. 18 at 10:30 a.m. and 1:30 p.m. The Nov. 4 session includes a post office visit.
Deb Paton Showley Group will keep following the Waubee Lake Trail through the January bid opening and into construction. If you live near the route along First Street, 1150 North or Camp Mack Road and want to talk about what a finished trail could mean for your property, Deb Paton Showley Group is happy to help.