Crews were scheduled to start closing Epworth Forest Road on Tuesday, Nov. 17, for about a week. They are tying the existing Knapp Lake force main into new sewer pipe along Webster Lake's east shore, and Knapp Lake's wastewater is being trucked to North Webster while the work goes on, InkFreeNews reported. As of the sewer board's Nov. 9 meeting, about 88% of the mainline pipe was in the ground. Only 37% of the smaller pressure laterals and 10% of the grinder stations had been installed.
Pipe in the road comes first. Getting sewer to each house is the second stage, and it takes longer. The best guide to how long is the same district's last project, around Chapman Lake and Tippecanoe Lake.
Where the pipe runs
The East Webster project is an expansion of the Tippecanoe and Chapman Regional Sewer District. Its service area covers the eastern section of Webster Lake. It is bounded roughly by Epworth Forest Road on the north, N 950 E and Backwater Road on the east, and the Backwaters Public Access site on the south. The state's January 2026 environmental notice for the project lists about five miles of pressure sewer and about 150 grinder-pump stations. Those stations will replace about 200 residential septic systems, including those at Webster Bay Mobile Home Park. The district's December 2023 engineering report also counted Sock's Marina in its flow calculations.
The engineering report gives three reasons for the project: aging septic systems, lots too small to keep enough distance from private wells, and soils poorly suited to septic. It estimated that 166 of the systems in the area, or 83%, were past their useful life. Webster Lake covers 653 acres and reaches 52 feet at its deepest, according to the Lilly Center for Lakes & Streams. At the February rate hearing, Webster Lake Conservation Association president Michael Wyrick said septic systems contribute to weeds and poor water quality and argued that sewer would protect the lake, InkFreeNews reported.
What it costs each month
Baker Tilly consultant Jeff Rowe put the full project at about $7.4 million. A $5 million State Revolving Fund grant covers most of it, and a long-term, low-interest SRF loan covers the rest. On Feb. 9, 2026, the board gave final approval to two monthly rates per equivalent dwelling unit: $60.90 during construction, then $110 once the project is finished and connections are required. The construction-period bills have already started. The district had collected about $25,000 in partial user fees and meter charges through May 31, 2026.
Chapman Lake and the two Tippecanoe Lake areas, which are already on the district's system, make a useful comparison. Their single-family charge is $88.35 a month under the district's amended rate ordinance, dated December 2025. At the $110 rate, a finished east-shore Webster Lake home will pay $1,320 a year for sewer, about $260 more than a Chapman or Tippecanoe home pays at $88.35. These figures are general information, not legal, tax or financial advice, so confirm your own property's numbers with the district and the right professional before you write an offer.
How the last rollout went
The district finished building sewer around Chapman Lake and both sides of Tippecanoe Lake in January 2025, after five years of work by a volunteer board. At that point, 66% of Chapman Lake properties were connected, along with 15.8% on Tippecanoe Lake West. Connections on Tippecanoe Lake East had not started. Chapman owners had been able to connect since July 18, 2024.
The table below follows the rollout from there, based on InkFreeNews coverage of the board's monthly meetings.
| Date | Original district connection status |
|---|---|
| January 2025 | Construction complete; 552 of 1,811 connections done |
| June 2025 | About 59% connected; board voted to extend its deadline |
| End of February 2026 | 90% connected; 137 properties still unconnected |
| May 2026 | Board approved $1-a-day penalties for remaining Contract A properties |
| Sept. 14, 2026 | 52 properties unconnected; board voted penalties for Contract B |
The first Chapman connections started in July 2024, and the district reached 90% about 19 months later. In June 2025, engineer Steve Henschen of Jones Petrie Rafinski described a Chapman Lake contractor with 50 customers lined up and no permit applications filed yet, InkFreeNews reported. Board president Jeff Thornburgh said at the same meeting, "Winter's coming, and we want this wrapped up by November." By September 2026 the district was still working through its last few dozen properties.
That record suggests what to expect on Webster Lake's east shore. The engineer has said hookups will not start until the district sends a letter saying the project is done. Substantial completion is currently targeted for around the beginning of May 2027. The Chapman and Tippecanoe rollout did not go from completion to every house connected in one season. If East Webster follows a similar pattern, east-shore homes listed in 2027 and 2028 will be at different stages: still on septic, connected, or with a connection contracted and waiting on a crew.
What that means in a purchase
On this shore, ask about sewer status for every listing. A buyer touring a house next spring may find a working septic system and a grinder station already in the yard but not yet hooked up. A house down the road may be fully connected. These two homes carry different costs in the months after closing, even if their list prices look alike. On the seller's side, a house already connected when it goes on the market answers a question most east-shore buyers will ask.
Easements are mostly settled. The district has secured 196 easements, and four remain outstanding. Two of the four involve grinder stations shared with a neighboring property. The engineer said meetings would be arranged with the affected owners. When a home's grinder station sits on or serves a neighboring parcel, that arrangement belongs in the buyer's due diligence along with the survey.
The district has stayed on budget and on schedule. At the Nov. 9 meeting, about 33% of contracted work was complete with about 55% of the contract time elapsed, and Henschen said construction was consistent with the contractor's schedule. Crews were installing two or three grinder stations a day, with a second crew expected to join next month. About $405,000 remained in contingency, and no new change orders were approved. Rowe also reported that operating revenue for the original service area was $128,000 above budget through October, and the district held about $1.3 million in reserves beyond its required minimums. The district negotiated the Knapp Lake capacity contribution down to $20,000 under an interlocal agreement approved in December 2025.
Owning a house on grinder-station sewer
Once the house is connected, upkeep changes. The district's grinder-station user guide tells owners what to do when the alarm sounds: stop using water, silence the panel and wait 15 minutes for a high-water alarm to clear. If it does not clear, call the service line. The district responds to grinder-station problems, while the owner is responsible for blockages in the private sewer lateral. Astbury Water Technology operates the system, and its grinder-station emergency line is 1-888-804-2601.
Household water equipment also matters. InkFreeNews reported in June 2025 that the district was dealing with grinder-station alarms set off by water softeners. On a lake home with a well, a softener and a filtration system, ask how that equipment drains before closing. The same question applies on Chapman and Tippecanoe, where these systems are already running.
Power outages are handled at the district level. According to InkFreeNews, after an Oct. 15 power failure the backup generator at Lift Station No. 2 did not start because a transfer switch malfunctioned, and a small overflow resulted. Technicians replaced a failed battery and updated the switch's firmware.
FAQ
When can east-shore Webster Lake homes connect? Substantial completion is targeted for around the beginning of May 2027. The project engineer has said hookups start after the district notifies owners that the project is done.
Is my parcel inside the service area? The east-shore boundary runs roughly from Epworth Forest Road to Backwater Road and the Backwaters Public Access site. The district's Webster Lake east shore page has a boundary map and a contact for questions about a specific property.
Where can I follow the project? The board meets monthly at the North Webster Community Center, and its next regular meeting is Monday, Dec. 14. More on the town is on our North Webster neighborhood page, and we have also written about docks and septic on Lake Wawasee.
If you own on Webster Lake's east shore and are wondering whether to list before or after your connection, or you are a buyer weighing two houses at different stages of the switch, Deb Paton Showley Group can go through the timeline and the numbers for your property. For a current read on what your home is worth now, start with our home valuation.